1、To gain visibility of performance issues, a quality assurance report recommends that changes be made in the project measurement process. However, if the changes are implemented, it will impact the customer’s delivery date. What should the project manager do next?
A. Inform the sponsor and ask for advice regarding how to address the situation.
B. Implement the changes to meet the required visibility of the performance issues.
C. Secure the delivery date for the customer and do not implement the changes.
D. Evaluate the impact of implementing versus not implementing the changes.
为获得性能问题的可见性,一份质量保证报告建议在项目测量过程进行变更。但是,如果实施变更,将会影响到客户的交付日期。项目经理接下来应该怎么做?
A.通知发起人,并询问如何解决这种情况的相关建议。
B.实施变更,满足要求的性能问题可能性。
C.为客户实施交付日期,但并不实施变更。
D.评估实施变更和不实施变更的影响。

2、During a critical component's development, a senior employee leaves the project. As a result, the project is behind schedule. During the planning phase, the probability of the risk occurring was determined to be low, and the impact was medium. What document should the project manager update first?
A. Risk register
B. Risk management plan
C. Work breakdown structure
D. Staffing management plan
在关键部件开发过程中,一名高级雇员离开项目。结果,项目落后于进度。在规划阶段,发生风险的可能性被确定为低,影响为中等。项目经理应首先更新哪一份文件?
A.风险登记册
B.风险管理计划
C.工作分解结构
D.人员配备管理计划

3、Due to a personal situation, a project team member is tired, cannot focus on their work, and is behind schedule. What should the project manager do?
A. Support the team member by sending the team member home to get rest
B. Ask management to replace the team member
C. Take disciplinary action against the team member
D. Notify management that the schedule will slip
一名项目团队成员因个人原因感到疲劳,无法专注其工作并导致项目进度落后。项目经理应该怎么做?
A. 支持团队成员,并让他们回家休息
B. 要求管理层替换该团队成员
C. 针对团队成员采取纪律措施
D. 通知管理层项目进度将落后

4、A product is delivered on time, delivered within cost, and meets quality expectations. However, the project team is not sure if the product produced meet the client’s requirements. Which of the following explains this situation?
A.There was poor communication among stakeholders
B. Project chart was incomplete
C.Expert judgment was not used during the requirement identification phase
D.Requirements traceability matrix was not being updated
一个产品按时按成本交付,并满足质量期望。但是,项目团队不确定生产的产品是否满足客户需求。下列哪一项说明了这种情况?
A.干系人之间的沟通不良。
B.项目章程不完善。
C.在需求识别阶段未使用专家判断。
D.未更新需求跟踪矩阵。
信息系统项目管理师每天一练-30

1、答案:D。解析:先评估变与不变的影响,再来决定下一步措施。
2、答案:A。解析:风险发生后,应该更新风险登记册的信息。
3、答案:A。解析:采用人性化管理。

4、答案:A。解析:沟通没有到位,没做好沟通反馈。
注意:以上仅为练习题,并非真题

信息系统项目管理师每天一练-30
 
免责声明:以上便是【信息系统项目管理师每天一练-30】的全部内容。大多文章纯属本网站原创,部分文章信息来源于网络以及网友投稿,本网站只负责对文章进行整理、排版、编辑,是出于传递更多信息之目的,并不意味着赞同其观点或证实其内容的真实性,如本站文章和转稿涉及版权等问题,请作者在及时联系本站,我们会尽快处理。
标题:信息系统项目管理师每天一练-30 地址:https://www.hxtdpx.com/PMPkstk/5560.html

PMP近期热点

学员感言

1.来自广州的赵同学:

在朋友的推荐下选择了有优培东方(原广州慧翔),经历了时长两个月的pmp培训,过程虽然辛苦,但是结果说明了一切优培东方(原广州慧翔)的老师认真负责专业,特别是刘老师在线上课讲解pmbok难点考点,还悉心答疑。经过优培东方(原广州慧翔)PMP培训过程,我一次性5A通过了考试,希望更多的人选择优培东方(原广州慧翔),通过有效的过程能提高你的通过几率!

2.来自深圳的王同学:

报读优培东方(原广州慧翔)也是对比了几家之后才报的,讲课老师辅导老师都非常专业,主要是看中优培东方(原广州慧翔)的服务,包括网络课(不同的班还有面授课程)+超级全面的海量题库练习包括单元的综合的重点题的+模拟考试+讲解+考前辅导与评估(这很重要)能够给出专业评价并辅助预估通过可能性……总之很棒,跟上老师节奏都可以轻松通过,不错的培训机构,个人非常认可。

3.来自上海的陈同学:

很早接触项目管理而且工作,但由于公司要求有PMP认证证书才能正式命名为项目经理,后经同事(同事是在优培东方(原广州慧翔)机构顺利拿到PMP证书)介绍,报名参加了优培东方(原广州慧翔)PMP培训。 为了让我们学生能顺利通过PMP考试并获取到证书,刘老师总是不怕辛苦坚持利用每周4-5天晚上时间及安排的面授公开课方式,生动、切合实际地将枯燥乏味项目管理理论结合实际的案例及其生动幽默的方式进行讲解,授予学生学习方法和思路,结合刘老师的教学方式和方法,通过几个月的自身学习,使得顺利通过考试。

4.来自北京的王同学:

优培东方(原广州慧翔)是我工作以后接触的第一个培训机构,2015年的时候由于工作需要,我想报考PMP。但是市场上各种各样的机构太多了,各种评价褒贬不一。但是通过分析之后,我选择了优培东方(原广州慧翔)PMP培训。事实证明,做了调查后作出的选择不会太差,通过接近3个月的准备学习之后,我在第一次PMP考试时就顺利通过了PMP认证,拿到了PMP证书。本以为拿完证书后跟慧翔就算是byebye了,但是更可贵的资源才开始。通过优培东方(原广州慧翔)的学友群,我们定期组织活动,群上跟学友交流,认识了更多的同行朋友,甚至可以说获得了更多的资源资讯。 最后,认真地说如果想学PMP,我推荐优培东方(原广州慧翔)。