A. Responsibility assignment matrix
B. Project scope statement
C. Quality management plan
D. Requirements traceability matrices
在用户对项目可交付成果开展验收测试时,客户发现其中一个关键功能未被识别。项目经理下一步应该与客户审查哪一项?
A. 职责分配矩阵
B. 项目范围说明书
C. 质量管理计划
D. 需求追溯矩阵
2、After indentifying a risk that will negatively impact a project, the project team contracts an insurance company to manage the risk effects, Which of the following risk strategies was used?
A. Avoid
B. Transfer
C. Mitigate
D. Share
识别到一个将对项目产生负面影响的风险后,项目团队在一家保险公司投保来管理风险影响。这使用的是下列哪一项风险策略?
A.回避
B.转移
C.减轻
D.分享
3、A project manager discovers a key feature of the deliverable deviates from the customer’s original specification, but meets quality and legal requirements. With budget and schedule constraints team members suggest keeping the original design, while other team members insist on modifying the design to meet the customer’s requirement. After negotiation, the final decision is to keep the current design.The project manager should take which of the following actions next?
A. Follow the risk response matrix
B. Change the quality plan
C. Update scope management plan
D. Follow the change management procedure
项目经理发现可交付成果的一个关键功能与客户的原始技术规定存在偏差,但是满足质量和法律要求。在预算和进度都有制约的情况下,一些团队成员建议保留原始设计,而另一些团队成员坚持改变设计,满足客户的需求。协商之后,最终决定还是保留当前设计。项目经理下一步应该采取下列哪一项措施?
A. 遵循风险响应矩阵
B. 变更质量计划
C. 更新范围管理计划
D. 遵循变更管理程序
4、The project is half way to completion and continues to be over budget. The current project metrics are as follows: Schedule Performance Index (SPI) =0.96 Cost Performance Index (CPI) =0.98 Actual Cost (AC) =500,000 Budget at Completion (BAC) =1,000,000 Which of the following is the expected total cost of completing all work?
A. US$1, 505, 024
B. US$1, 101, 666
C. US$1, 020, 408
D.US$990,073
项目处于完工中途,并继续超出预算。当前的项目指标如下:
进度绩效指数(SPI)=0.96
成本绩效指数(CPI)=0.98
实际成本(AC)=500,000
完工预算(BAC)=1,000,000
下列哪一项属于完成全部工作的预计总成本?
A. US$1,505,024
B. US$1,101,666
C. US$1,020,408
D. U$990,073
1、答案:D。解析:功能没有识别出来,PM要和客户查看需求追溯矩阵,看看客户到底有没有提过这个需求。
2、答案:B。解析:买保险属于风险转移。
3、答案:D。解析:虽然满足法律和质量要求,但是“关键功能与客户的原始技术规定存在偏差”,与原始相比是有变化的。遵循变更管理流程。
4、答案:C。解析:典型偏差:EAC=BAC/CPI=1000,000/0.98=1020408
注意:以上仅为练习题,并非PMP考试真题