项目相关单位责任矩阵
P 一主要责任/主持召集;S-提供支持/参与;R-审核/监控;A-批准
|
序号 |
工作分解
|
相关单位 |
|||||
|
业主 |
PM |
总包 |
供应商/分包 |
监理 |
设计
|
||
|
项目总体管理 |
|||||||
|
1 |
编制项目的综合管理计划 |
A |
P |
S |
S |
S |
|
|
2 |
工程例会 |
|
P |
S |
S |
S |
|
|
3 |
进度监控、报告 |
|
P |
S |
S |
S |
|
|
4 |
现场施工组织 |
|
R |
S |
R |
|
|
|
5 |
现场管理 |
|
|
P |
R |
S |
|
|
合同/招标/采购管理 |
|||||||
|
1 |
招标计划、内容(标的)范围编制 |
A |
P |
S |
S |
|
S |
|
2 |
招标文件/其它相关手续 |
|
P |
|
|
|
S |
|
3 |
招标文件审核 |
A |
P |
|
|
|
|
|
4 |
考察/询价/评标 |
|
P |
S |
S |
S |
S |
|
5 |
定标 |
A |
P |
|
|
|
|
|
6 |
合同商签 |
A |
P |
|
S |
|
|
|
7 |
合同管理 |
|
P |
|
S |
S |
|
|
8 |
供货催交 |
|
P |
S |
S |
S |
|
|
9 |
合同管理收尾 |
|
P |
|
S |
S |
|
|
成本控制管理 |
|||||||
|
1 |
编制成本分解结构(cBs) |
A |
P |
S |
|
|
|
|
2 |
成本估算&预算 |
A |
P |
|
|
|
|
|
3 |
编制资金使用计划 |
A |
P |
S |
|
|
|
|
4 |
审核月进度款请求 |
A |
P |
S |
S |
P |
|
|
5 |
变更的审核&批准 |
A |
P |
S |
S |
|
S |
|
6 |
成本预测&成本汇报(成本绩效分析)
|
|
|
S |
S |
|
|
|
7 |
工程结算/保修期成本管理 |
A |
R |
P |
|
R |
|
|
质量控制管理 |
|||||||
|
1 |
编制质量管理计划 |
A |
R |
S |
S |
P |
S |
|
2 |
施工单位(供应商)质量管理体系及落实情况 |
|
R |
S |
S |
P |
|
|
3 |
工程实体施工(含进场设备材料)质量控制
|
|
R |
S |
P |
S |
|
|
4 |
施工过程质量控制(重点旁站 |
|
R |
S |
P |
S |
|
|
5 |
质量问题整改监控 |
|
R |
S |
P |
|
|
|
6 |
施工质量情况报告 |
|
S |
S |
P |
|
|
|
7 |
分部、分项质量验收 |
|
R |
S |
P |
S |
|
|
进度控制管理 |
|||||||
|
1 |
编制总体施工进度控制计划 |
A |
R |
P |
S |
S |
|
|
2 |
编制短期作业进度表 |
|
|
P |
S |
R |
|
|
3 |
施工进度跟踪对比/报告 |
|
R |
P |
S |
S |
|
|
4 |
施工进度协调会议 |
|
P |
S |
S |
S |
S |
|
5 |
进度更新&维护 |
A |
R |
P |
S |
|
|
|
信息/沟通/资料文件/报告管理 |
|||||||
|
1 |
建立信息管理框架 |
A |
P |
S |
|
S |
|
|
2 |
沟通管理计划 |
A |
P |
S |
S |
S |
S |
|
3 |
文件管理控制要求 |
|
P |
S |
S |
S |
S |
|
4 |
文件标准格式、模板 |
|
P |
S |
S |
S |
S |
|
5 |
工程综合管理报告 |
A |
P |
S |
S |
S |
|
|
6 |
会议纪要、分发 |
|
P |
S |
S |
S |
|
|
7 |
各项验收报告 |
|
|
P |
S |
R |
|
|
8 |
操作&维护手册 |
|
|
S |
P |
R |
|
|
9 |
工程资料档案 |
|
|
P |
|
S |
|
|
10 |
竣工图 |
|
|
P |
S |
R |
|
|
11 |
项目总结 |
A |
P |
S |
|
S |
|
|
安全、文明、环保 |
|||||||
|
1 |
现场安全文明施工计划 |
|
A |
P |
R |
S |
|
|
2 |
安全文明施工体系建立、落实情况 |
|
|
P |
R |
S |
|
|
3 |
安全文明施工情况检查 |
|
|
P |
S |
R |
|
|
4 |
问题整改、检查 |
|
|
P |
S |
R |
|
|
5 |
事故汇报&应急反应 |
|
|
P |
S |
|
|
|
6 |
安全文明施工报告 |
|
A |
S |
S |
P |
|
|
风险管理 |
|||||||
|
1 |
编制风险管理计划 |
A |
P |
S |
|
S |
|
|
2 |
识别施工过程风险因素 |
|
P |
S |
S |
S |
|
|
3 |
风险分析 |
|
P |
S |
|
S |
|
|
4 |
风险应对措施 |
A |
P |
S |
S |
S |
|
|
5 |
风险监控 |
|
P |
S |
|
S |
|
|
预验收/试车管理 |
|||||||
|
1 |
编制综合验收计划 |
A |
R |
S |
S |
P
|
|
|
2 |
组织&协调 |
S |
P |
S |
S |
S |
|
|
3 |
确定验收文件标准格式 |
|
P |
S |
S |
S |
|
|
4 |
组织实体验收 |
S |
S |
S |
S |
P |
|
|
5 |
组织资料验收 |
S |
S |
S |
S |
P |
|
|
6 |
整理问题清单 |
|
A |
P |
S |
R |
|
|
7 |
督促整改 |
|
|
S |
S |
P |
|
|
8 |
审核系统性能&验收测试结果 |
|
R |
S |
S |
P |
|
|
9 |
联系相关政府部门(消防、规划、安全、环保等) |
|
P |
S |
|
|
|
|
10 |
使用方相关人员培训准备 |
|
P |
S |
S |
|
|
|
最终验收、质量监督备案 |
|||||||
|
1 |
消防 |
|
P |
S |
S |
S |
|
|
2 |
规划 |
|
P |
S |
S |
S |
|
|
3 |
安全 |
|
P |
S |
S |
S |
|
|
4 |
环保 |
|
P |
S |
S |
S |
|
|
5 |
卫生 |
|
P |
S |
S |
S |
|
|
6 |
绿化 |
|
P |
S |
S |
S |
|
|
|
质监站 |
|
P |
S |
S |
S |
|
|
移交使用方、工程保修 |
|||||||
|
1 |
工程实体移交 |
|
P |
S |
S |
S |
|
|
2 |
工程资料移交 |
|
P |
S |
S |
S |
|
|
3 |
工程资料提交城市建设档案馆 |
|
P |
S |
S |
S |
|
|
4 |
签订工程保修合同 |
|
P |
S |
S |
S |
|
|
5 |
工程质量保修 |
|
P |
S |
S |
S |
|